Concrete Calculator

Work out how much concrete a slab, footing, column, curb or set of steps needs, in cubic yards and in 40, 60 or 80 lb premix bags.

Patios and walks are usually 4 in; driveways 5–6 in.
5–10% is typical.
Cubic feet
36.67 ft³
Cubic meters
1.038 m³
Before waste
1.23 yd³33.33 ft³
80 lb bags
620.60 ft³ each
60 lb bags
820.45 ft³ each
40 lb bags
1230.30 ft³ each
Weight once placed
5,320 lb≈ 2.7 tons at ~145 lb/ft³
Concrete needed1.36 yd³including 10% extra
  • At a cubic yard or more, ready-mix delivery is usually cheaper and easier than mixing bags; ask suppliers about short-load fees.
  • Bag yields vary slightly by brand; check the label.

Show the work

  1. Slab: 10 ft × 10 ft × 4 in = 10 × 10 × 0.3333 ft = 33.333 ft³
  2. Add 10% waste: 33.333 × 1.1 = 36.667 ft³ ÷ 27 = 1.36 yd³
  3. 80 lb bags: 36.667 ft³ ÷ 0.60 ft³ per bag = 61.11 → 62 bags
Premixed bag options
Bag sizeYield per bagBags neededTotal weight
80 lb0.60 ft³624,960 lb
60 lb0.45 ft³824,920 lb
40 lb0.30 ft³1234,920 lb

Concrete is sold by the cubic yard and in bags by weight, but projects are measured in feet and inches. This calculator handles the conversion for the shapes you are most likely to pour — rectangular slabs, footings and walls, round columns, hollow tubes, curb and gutter runs, and steps — and tells you how many yards to order or how many premix bags to buy.

How to use the concrete calculator

  1. Choose the shape you are pouring.
  2. Enter each dimension and pick its unit. You can mix units freely, such as feet for length and inches for thickness.
  3. Enter the number of identical pours — for example, eight fence-post holes of the same size.
  4. Set the extra for waste; 10% is a sensible default for most DIY pours.
  5. Read the total in cubic yards, cubic feet and cubic meters, and compare the 40, 60 and 80 lb bag counts.

Concrete volume formulas

The calculator converts every dimension to feet, finds the volume in cubic feet, and divides by 27 for cubic yards.

Slab: V = L × W × T  ·  Column: V = π × (d ÷ 2)² × h
Tube: V = π ÷ 4 × (D² − d²) × h
Curb and gutter: V = L × [c × (h + f) + g × f]

For curbs, c is curb depth, h is curb height above the gutter, g is gutter width and f is the flag (gutter) thickness. Steps are treated as solid blocks down to grade: step i is one tread deep and i risers tall, so the side profile is run × rise × (1 + 2 + … + n), plus any top landing, multiplied by the stair width.

Bag counts divide the total by each bag’s yield and round up:

bags = ⌈ volume (ft³) ÷ yield per bag ⌉

Worked example: a 10 × 10 ft patio

Volume = 10 ft × 10 ft × (4 ÷ 12) ft = 33.33 ft³ = 1.23 yd³

With 10% extra: 33.33 × 1.10 = 36.67 ft³ = 1.36 yd³

80 lb bags: 36.67 ÷ 0.60 = 61.1 → 62 bags (or 82 bags of 60 lb, or 123 bags of 40 lb)

Sixty-two bags weigh nearly 5,000 pounds and take hours to mix by hand, which is why many builders switch to ready-mix at around a cubic yard.

Bags or ready-mix?

Bag size Typical yield Bags per cubic yard
40 lb 0.30 ft³ 90
60 lb 0.45 ft³ 60
80 lb 0.60 ft³ 45

Bags make sense for post holes, small pads, steps and repairs. For larger pours, a ready-mix truck delivers consistent concrete all at once, which avoids cold joints between batches. Most trucks carry up to about 9 to 11 cubic yards; suppliers often add a short-load fee for small orders, so compare the price of bags against the delivered cost. Order ready-mix in quarter- or half-yard increments, rounding up.

Typical thicknesses

Project Common thickness
Sidewalk or patio 4 in
Residential driveway 4–6 in (5–6 in for trucks)
Garage or shop floor 4–6 in
Footing at least 6 in under the IRC; width depends on load and soil
Post hole 3 × the post width, below the frost line

These are common starting points, not engineering specifications. Your local building department, the project plans or an engineer set the actual requirements.

Why order extra

Subgrade is never perfectly flat, forms bow slightly under the weight of wet concrete, and some always ends up in the wheelbarrow or on the ground. A low spot of just a quarter inch across a 10 × 10 slab adds about 2 cubic feet. For the base under the slab, use the gravel calculator or road base calculator, and for plain volume conversions, the cubic yards calculator.

Frequently asked questions

How many bags of concrete make a cubic yard?

A cubic yard is 27 cubic feet. At typical yields, that takes about 45 bags of 80 lb mix (0.60 ft³ each), 60 bags of 60 lb mix (0.45 ft³) or 90 bags of 40 lb mix (0.30 ft³), before adding any extra for waste.

How thick should a concrete slab be?

Sidewalks and patios are commonly 4 inches thick. Driveways that carry cars are usually 4 to 6 inches, with 5 to 6 inches preferred for heavier vehicles. Local codes and your soil conditions can require more.

How much extra concrete should I order?

Adding 5 to 10 percent covers uneven subgrade, slight form bulging and spillage. Running short in the middle of a pour creates a cold joint, so it is cheaper to have a little left over than to need a second delivery.

How do I calculate concrete for a round column or tube form?

Use the cylinder formula: π × radius² × height, with all measurements in feet. A 12-inch tube 4 feet deep holds π × 0.5² × 4 ≈ 3.14 ft³, or about 0.12 cubic yards, which is roughly six 80 lb bags.

How much does a cubic yard of concrete weigh?

Normal-weight concrete is about 145 to 150 pounds per cubic foot, so a cubic yard weighs roughly 3,900 to 4,050 pounds — about two tons. That matters if you plan to haul premix in a pickup.

Last reviewed October 2026 by the CalcFluent editorial team. How we check our calculators.